Construction Update
Scroll down our chronological photojournal to see the progress.

July 10, 2007
The long awaited start of construction activity began officially on Tuesday, July 10, with the arrival of the Wickersham Construction site trailer. Tools and equipment continue to arrive daily as the crew begins the early stages of re-modeling the current fellowship hall into an educational wing that will feature eight new classrooms.

The target date for completion of this first phase of the project is early September, 2007. The start of new construction is scheduled for late September, with plans to have the new building under cover by Christmas, 2007. This phase of the project will see the addition of a new Fellowship Hall with an upgraded kitchen; a new Administrative wing, conference room, restrooms, storage areas, and Youth Room. Upon the completion of this phase, the final renovations will take place which will include a new Music Suite, an expanded narthex/parlor area and pre-school classroom.

August 3, 2007
Construction crews have been hard at work taking down walls, folding partitions, the drop ceiling, old light fixtures and HVAC ductwork since their arrival in July. They have removed the old carpeting and the floor tiles beneath the carpet exposing the original concrete slab. A second thickness of drywall has also been added to the existing ceiling this past week to meet fire code regulations.

This is tedious, time-consuming work, but necessary work as we prepare for the new education wing that will soon begin taking shape. The footprint of the new building has been staked out and gives one a better sense of the entire scope of the project.


September 10, 2007

We are ready to move into this renovatedl wing! Dedication is Septmber 16. This area has changed from worship center to fellowship hall and now to the education wing.
.
.
September 16, 2007
The education space was opened with the officail ribbon cutting,

Our new large classroom

Cathy Spence and youth cut the ribbon to officailly open the new education wing.
September 30, 2007
Groundbreaking for the new fellowship wing was September 30.

Congregation assmbles at noon on September 30, 2007 to break ground for the new wing.

Pastor DeRasmo turns the first three spades of soil.

Bill Vann, Congregational President; Bernie Langer, Chair of the New Building Committe; and Darwin Wika, Chair of the New Building Finance Committee participated in the offical ground breaking service.

Pastor Conrad and others join in.
October 23, 2007

The concrete truck finally arrives.

Pouring concrete footers



And so, our fellowship/office wing begins to take shape
November 28, 2007

Concrete trucks arrive for the big day

Pouring the concrete slab.

Spreading the concrete

Leveling the concrete

Finishing off the pour

Working on the new parking lot.
December 6, 2007

Amish workers arrive to frame the building

New Youth Room is framed

Erecting the walls of the Fellowship Hall

Framing being lifted into place. Trusses just a week away.
December 17, 2007

First walls taking Shape
New restrooms and Storage Areas
January, 2008

Steel Trusses Erected

Wood Trusses Erected

Amish Workers Putting Trusses in Place

Crane lifting trusses to roof

February, 2008

Roof under cover

Exterior of the Youth Room

Truses Up, no Walls

Under Cover
March, 2008

The beginnings of the new Church Office Suite

New Entrance Taking Shape


The New Youth Room